0

Concrete is a homogeneous mixture of cement, coarse aggregate, fine aggregate(sand) and water. In addition to the above concrete needs the use of special materials which is admixture to reduce the water-cement ratio of mix. Mineral or Chemical Admixtures are generally used for construction as per requirement. Nowadays, concrete is the most used construction materials throughout the world. Before Start of Concreting in any construction, there must be proper planning and checklist which have to follow.

SECTION: 1.0

1.1

Before Start of Concreting in Construction Project:

  • Obtain contract documents including drawings and programme
  • Visit site for ascertaining the availability for access, services and space for working areas.
  • Summarize principal quantities
  • Assess sources of materials
  • Assess the availability of construction plant and output

1.2

Required Technical information before Construction:

  • For each mix, obtain information regarding the following:
  1. Type and grade of concrete
  2. Type of cement
  3. Standard and maximum size of aggregate 
  4. Minimum and maximum cement content
  5. Admixtures, if any 
  6. Workability 
  7. Water cement ratio
  • Obtain the following information regarding concreting: 
  1.  Surface finish and formwork 
  2. Temporary works design to be submitted 
  3.  Reinforcement
  4.  Testing requirements
  5.  Ancillary items 
  • Any special restrictions/information to be provided

1.3

Planning Before Start of Concreting in Construction Project:

  • Prepare a site management plan
  • Design temporary works
  • Design formwork reuse system
  • Prepare test programme for approval of materials 
  • Calculate labour requirements and output targets
  • Sketch provisional site layout
  • Assess daily concrete demand
  • Assess the rate of pour for individual components

1.4

Project Decisions:

  • Decide on the following:
  1. Output and type of batching/mixing plant 
  2. Location of plant and materials 
  3. Method and capacity for transporting concrete
  • Decide upon equipment for compaction, finishing and curing
  • Decide the location of bar bending yard
  • The select materials control system

1.5

Action Before Concreting in Construction Activity:

  • Obtain technical approval for the following: 
  1. Materials including mix design and sample panel
  2. Temporary works design
  3. Tolerances
  4. Method and sequence of working
  • Calculate batch weights for concreting 
  • Arrange materials
  • Arrange connection of services
  • Arrange to provide construction plant
  • Obtain testing equipment

1.6

Initial Construction Setup after site occupation:

  • Establish a communication system
  • Erect. calibrate and commission concrete production plant
  • Connect water and power supply
  • Construct workshop and storage facilities
  • Organize receipt and issue arrangements for materials
  • Provide trial mixes for onsite work
  • Calibrate construction equipment
  • Organize spares and standby equipment
  • Prepare maintenance schedule for equipment 
  • Establish testing facilities
  • Confirm testing arrangements and compliance procedures with the clients
  • Prepare a detailed plan for each pour:
  1. The method including plant and labour 
  2. Materials and built-in items
  3. Formwork
  4. Testing

SECTION: 2.0

2.1

Pre Concreting Checks in Construction:

Pre Concreting Checks in Construction

2.1.1

General Inspection Before Concreting:

  • Confirm availability of:
  1. Materials
  2. Labour
  3. Plant and equipment
  4. Power and water supply
  5. Standby and spares
  • Confirm setting out has been checked 
  • Confirm earlier permanent work inspected
  • Obtain weather forecast
  • Check the adequacy of:
  1. Access to points of discharge
  2. Access platforms
  • Confirm readiness of batching plant
  • Check communications system
  • Confirm compliance with safety regulations
  • Confirm arrangements for:
  1. Transporting
  2. Placing
  3. Compacting
  4. Finishing
  5. Curing
  6. Testing

2.1.2

Surfaces Check Before Concreting in Construction:

  • Falsework for:
  1. Conformity with design
  2. Stability
  3. Rigidity
  4. Pre-camber
  • Formwork for:
  1. Conformity of dimensions to within allowable tolerances 
  2. Strength and rigidity 
  3. Correct use and number of ties
  4. Provision of the surface to comply with the specification
  5. Tightness and sealing of joints
  6. Final clean-up before concreting
  7. Arrangement for removal

2.1.3

Joints, Inserts and Openings Check Before Concreting in Construction:

  • Construction of joints, dowels, water bars and sliding layers
  • Inserts and box-outs for accuracy and security
  • Fixing of stop-ends
  • Arrangements for forming kickers
  • Preparation of hardened surfaces

2.1.4

Reinforcement check before Concreting:

  • Correct diameter, shape, type, location and cover
  • Correct diameter, shape, type, location and cover
  • Rigidly secured
  • Surface condition
  • Use of spacers including type and size

SECTION: 3.0

3.1

Site Batching and Mixing of Concrete:

  • Weigh scale calibration record
  • Material storage facilities and availability of supplies
  • Arrangement for workability control
  • Batch record cards and procedure

SECTION: 4.0

4.1

Check During Transportation of Concrete:

  • For transportation system check routes free from obstruction. 

4.2

During Concreting Checks:

4.2.1

Check During the placing of Concrete:

  • Adequacy of workability
  • No segregation
  • No movement of reinforcement or formwork
  • No contamination

4.2.2

Checks during compaction of Concrete:

  • Adequate availability of compaction equipment
  • Equipment used correctly 
  • Adequate labour available 
  • Grout tightness of formwork

4.2.3

Checks during finishing of Concrete:

  • Availability of sufficient tools 
  • Adequate skilled personnel available 
  • Access platforms in position 
  • Protected against physical damage

SECTION: 5.0

5.1

Post Concreting Checks in Construction:

5.1.1

Checks during curing of Concrete:

  • Concrete is adequately and continuously protected against:
  1. Loss of moisture
  2. Extremes of temperature
  3. Drying winds 
  • Curing procedures maintained for a specified period

5.2

Removal of Formwork and Inspection:

Removal of Formwork and Inspection

5.2.1

Before removing formwork:

  • Check the adequacy of concrete strength
  • Identify props to be left in place 
  • Check safety arrangements
  • Confirm arrangements for treated surface finishes and joint preparation. 
  • Obtain authority for removal of formwork and falsework

5.2.2

After removing formwork:

  • Compare surface finish with specification or sample
  • Check for defects, including:
  1. Segregation, honeycombing or cavities
  2. Cracking
  3. Misalignment or dimensions outside tolerances
  4. Physical damage on stripping
  • In the event of any non-compliance:
  1. Decide upon possible alternative remedial measures 
  2. Obtain approval for proposals
  3. Carry out any trials required
  • Organize the collection and cleaning of all formwork and falsework items 
  • Inspect formwork and falsework to assess suitability for further reuse

SECTION: 6.0

6.1

Initial Sampling and Testing for Concreting in Construction:

6.1.1

General Quality Control checks:

  • General technical requirements from the specification for:
  1. Materials to be tested
  2. Properties to be measured
  3. Methods of the test to be employed 
  4. Rates of sampling/testing
  5. Test facilities
  • Format for report forms
  • Action to be taken in the event of non-compliance
  • Open test registers

6.1.2

Laboratory Testing equipment Checks:

  • For site laboratory:
  1. Confirm building and services available at the start of the contract 
  2. Ensure essential equipment available
  3. Check equipment complies with relevant standards 
  4. Check to measure equipment calibrated

6.1.2

Construction Materials Checks:

6.1.2.1

Prior to approval:

  1. Technical data on proposed sources of supply 
  2. Copies of recent test certificates 
  3. Samples for testing as required 
  4. Samples for testing as required
  • Conduct tests required for approval 
  • Submit results and apply for approval
  • Check the suitability of water for making concrete

6.1.2.2

After approval:

  • Aggregates: 
  1. Inspect each delivery to site
  2. Sample from stockpiles
  • Cement:
  1. Sample from each delivery 
  2. Obtain maker’s certificate
  3. Sample periodically from the site store or site.
  • Concrete:
  1. Agree on the place of sampling 
  2. Take a sample of adequate size for all tests
  3. Measure temperature
  • Other materials, including reinforcement:
  1. Sample at agreed rates
  2. Obtain maker’s certificates

6.2

Final Testing of Construction Material:

  • Aggregates:
  1. Carry out tests as required
  2. Submit reports 
  3. Complete test register
  • Concrete:
  1. Carry out tests on fresh concrete as required 
  2. Prepare specimens as required for strength tests
  3. Cure in the manner specified
  4. Measure density and conduct strength tests
  5. Submit reports
  6. Complete test register

6.3

Quality Control:

  • Calculate statistical data
  • Prepare quality control charts
  • Recommend changes to mixes and materials if appropriate
  • Undertake non-destructive tests on finished work if required.

Your Opinion Matters: How easy is it to understand the information on our website?

View Results

Loading ... Loading ...
0
Summary
Concreting in Construction - Planning and Execution
Article Name
Concreting in Construction - Planning and Execution
Description
Nowadays, concrete is the most used construction materials throughout the world. Before Start of Concreting in any construction, there must be proper planning and checklist which have to follow.
Author
Publisher Name
Construction Civil
Publisher Logo

WhiteHelmet

ConstructionCivil is a learning platform for all the Civil Engineers and Civil Engineering Students throughout the world. I have started this Website to educate and keep people notified by forming a trusted source of knowledge, everything related to Civil/Construction Engineering.
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments